How a build runs

Six stages.
One programme.

You get the programme with your quote, and a report against it every Friday.

Extension

About 22 weeks

Extension

About 22 weeks

Renovation

6 to 12 weeks

Renovation

6 to 12 weeks

New home

10 to 12 months

New home

10 to 12 months

Week

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

Groundworks

Frame

Roof and weathertight

First fix

Finishes and handover

Done · Wk 1 to 4

Site progress photo

Done · Wk 5 to 10

Site progress photo

On site now

Today

Maple Street extension · Live programme · Updated every Friday

Done

This week

Planned

The six stages

Where you are,
every week.

01

Groundworks and foundations

Wk 1 to 4

✓

02

Frame

Wk 5 to 10

✓

03

Roof and weathertight

Wk 11 to 14

04

First fix

Wk 15 to 18

05

Finishes and second fix

Wk 19 to 21

06

Snagging and handover

Wk 22

Roof timbers going on a new extension

Stage 03 · Weeks 11 to 14

Roof and weathertight

The roof goes on and the windows go in. From here the weather stops deciding the programme.

✓

Roof structure and covering

✓

Windows and external doors

✓

Inspection passed before first fix

You decide

Final window positions

You decide

Final window positions

We send

Photos of every elevation

We send

Photos of every elevation

Friday report

Week 14 of 22

Maple Street extension

Photo from this week on site
Photo from this week on site
Photo from this week on site

✓

Roof on and weathertight

✓

Windows and doors fitted

✓

First fix starts Monday

Sent Friday 4:02 pm by Sam Okafor

Every Friday

A report you can
read in two minutes.

✓

Photos of the week’s work

✓

What is done, against the programme

✓

What happens next week

✓

Any decision we need from you

Stage payments

You pay for what
is finished.

Five payments, each tied to a stage you can walk round and see.

Deposit

On signing. Covers design and permits

10%

Foundations

When groundworks pass inspection

20%

Weathertight

Roof on, windows in

30%

First fix complete

Plumbing, electrics and HVAC roughed in

25%

Handover

After the snagging walk-round

15%

Questions

About the programme.

What if it rains for two weeks?

−

Weather days are built into the programme up to weathertight. After that, rain does not move the date.

Can we change things once you have started?

+

Who do we talk to day to day?

+

What happens if you miss the date?

+

See a real build programme.

Ask for a sample and we will send the one from a job like yours.

Office open Monday to Friday, 7 to 5

See a real build programme.

Ask for a sample and we will send the one from a job like yours.