Juniper Court

New home

Juniper Court

Juniper Court

New home

Juniper Court

The brief

Four bedrooms on a narrow lot.

The lot in Littleton was forty feet wide with a neighbour close on each side. The owners wanted four bedrooms and a garden they could still use.

We built up instead of out and kept the whole ground floor open to the yard. It was handed over in ten months, for the price in the contract.

Project facts

Location

Littleton, Colorado

Type

New home, design and build

Size

2,900 sq ft, 4 bedrooms

Time on site

10 months

Fixed price

$980k, no changes

Juniper Court, kitchen

Kitchen

Juniper Court, living room

Living room

Juniper Court, main bathroom

Main bathroom

Juniper Court, dining

Dining

Juniper Court, street side at dusk

Street side at dusk

Programme against actual

Planned ten months. Took ten months.

01

Groundworks and foundations

Apr to May

✓

02

Frame

Jun to Jul

✓

03

Roof and weathertight

Aug

✓

04

First fix

Sep to Oct

✓

05

Finishes and second fix

Nov to Jan

✓

06

Snagging and handover

Feb, on the day

✓

$980k

Contract sum

0

Signed changes

$980k

Final invoice

43

Friday reports sent

Portrait of The Okafor family

From the owners

“The price on the first page of the contract was the price on the last invoice. We did not expect that to be true.”

The Okafor family

Owners, Juniper Court

Plan a project like this.

Start with a ballpark, then a site visit, then one fixed price.

Office open Monday to Friday, 7 to 5

Plan a project like this.

Start with a ballpark, then a site visit, then one fixed price.

Office open Monday to Friday, 7 to 5

Create a free website with Framer, the website builder loved by startups, designers and agencies.