The brief
One room, done properly.
The kitchen in this Boulder house had not been touched since 1988. The owners wanted oak, plaster and a layout that fits two cooks.
We stripped the room to the studs, moved the sink to the window and rewired the whole floor. Nine weeks, start to finish.
Project facts
Location
Boulder, Colorado
Type
Kitchen renovation
Size
310 sq ft
Time on site
9 weeks
Fixed price
$86k, no changes

Island and shelving

Tall cabinetry

Stone worktop

Kitchen to garden

Through the arch
Programme against actual
Planned nine weeks. Took nine weeks.
01
Strip out
Wk 1
✓
02
Plumbing and electrics
Wk 2 to 3
✓
03
Plaster
Wk 4
✓
04
Cabinets
Wk 5 to 6
✓
05
Worktops and tile
Wk 7 to 8
✓
06
Snagging and handover
Wk 9, on the day
✓
$86k
Contract sum
0
Signed changes
$86k
Final invoice
9
Friday reports sent

From the owners
“Nine weeks was the number on day one and nine weeks was the number at the end. We ate out less than we planned to.”
Helen Marsh
Owner, Larkspur kitchen