Maple Street extension

Extension

Maple Street extension

Maple Street extension

Extension

Maple Street extension

The brief

A kitchen that opens to the garden.

A 1920s brick house in Denver with a small dark kitchen at the back. The owners wanted room for a table and a wall that opens to the yard.

We added a single storey rear extension and stayed out of the rest of the house. The family lived at home for all twenty two weeks.

Project facts

Location

Denver, Colorado

Type

Rear extension, single storey

Size

420 sq ft added

Time on site

22 weeks

Fixed price

$186k, no changes

Maple Street extension, kitchen

Kitchen

Maple Street extension, island and shelving

Island and shelving

Maple Street extension, garden room

Garden room

Maple Street extension, from the garden

From the garden

Maple Street extension, at dusk

At dusk

Programme against actual

Planned 22 weeks. Took 22 weeks.

01

Groundworks

Wk 1 to 4

✓

02

Frame and roof

Wk 5 to 9

✓

03

Weathertight

Wk 10 to 12

✓

04

First fix

Wk 13 to 15

✓

05

Finishes

Wk 16 to 21

✓

06

Snagging and handover

Wk 22, on the day

✓

$186k

Contract sum

0

Signed changes

$186k

Final invoice

22

Friday reports sent

Portrait of Dana and Chris Whitlock

From the owners

“We cooked in the old kitchen until week sixteen. The dust stayed on the other side of the wall, as promised.”

Dana and Chris Whitlock

Owners, Maple Street extension

Plan a project like this.

Start with a ballpark, then a site visit, then one fixed price.

Office open Monday to Friday, 7 to 5

Plan a project like this.

Start with a ballpark, then a site visit, then one fixed price.

Office open Monday to Friday, 7 to 5

Create a free website with Framer, the website builder loved by startups, designers and agencies.