The brief
A working office, fitted out at night.
A design firm took two floors on Platte Street and had nine weeks before their old lease ended.
We ran two shifts, did the noisy work out of hours and handed over on the Friday before they moved in.
Project facts
Location
Denver, Colorado
Type
Commercial fit-out
Size
8,200 sq ft, two floors
Time on site
9 weeks
Fixed price
$612k, no changes

Window desks

Workspace

Reception

Lounge

Open floor
Programme against actual
Planned nine weeks. Took nine weeks.
01
Strip out
Wk 1
✓
02
Partitions
Wk 2 to 3
✓
03
Mechanical and electrical
Wk 3 to 5
✓
04
Ceilings and floors
Wk 5 to 6
✓
05
Joinery and finishes
Wk 7 to 8
✓
06
Snagging and handover
Wk 9, on the day
✓
$612k
Contract sum
0
Signed changes
$612k
Final invoice
9
Friday reports sent

From the owners
“We moved in on the Monday as planned. Nobody on our side had to chase anything.”
Renee Castillo
Operations lead, Platte Street office