Permits in Denver: what takes six weeks and why

Sam Okafor, site manager

Sam Okafor

Site manager

·

28 October 2026

·

5 min read

Permits in Denver: what takes six weeks and why

Most residential permits in Denver take four to eight weeks. Here is what happens in that time and how to keep it short.

The short answer

Our last 30 permit applications in Denver took between three and eleven weeks. The middle of that range was six.

The clock starts when the city accepts a complete application, not when you first send it in.

Typical review times, Denver

Kitchen or bath remodel

No structural change

2 to 4 weeks

Rear extension

Single storey, under 600 sq ft

5 to 8 weeks

New home

Full plan review

8 to 12 weeks

What slows a permit down

Most delays come from the same four places.

✓

Missing structural calculations

✓

Setbacks that need a zoning variance

✓

Historic district review

✓

Corrections not answered within a week

“A complete application saves more time than any phone call to the city.”

Three real examples

Maple Street extension

Rear extension, Denver

6 weeks

Larkspur kitchen

Renovation, Boulder

3 weeks

Cedar Ridge house

New home, Evergreen

10 weeks

What we handle for you

Drawings, structural calculations, the application and every correction. You sign the forms and we chase the rest.

How to start

Open the estimator for a range and a rough programme. The permit time is part of the written programme you get with the fixed price.

Sam Okafor, site manager

Sam Okafor

Site manager. Runs our Denver extension sites and every permit file.

Call Sam

→

Want the number for your house?

The estimator uses the same figures as our cost guides.

Want the number for your house?

The estimator uses the same figures as our cost guides.

Create a free website with Framer, the website builder loved by startups, designers and agencies.