Permits in Denver: what takes six weeks and why

Sam Okafor
Site manager
·
28 October 2026
·
5 min read

Most residential permits in Denver take four to eight weeks. Here is what happens in that time and how to keep it short.
The short answer
Our last 30 permit applications in Denver took between three and eleven weeks. The middle of that range was six.
The clock starts when the city accepts a complete application, not when you first send it in.
Typical review times, Denver
Kitchen or bath remodel
No structural change
2 to 4 weeks
Rear extension
Single storey, under 600 sq ft
5 to 8 weeks
New home
Full plan review
8 to 12 weeks
What slows a permit down
Most delays come from the same four places.
✓
Missing structural calculations
✓
Setbacks that need a zoning variance
✓
Historic district review
✓
Corrections not answered within a week
“A complete application saves more time than any phone call to the city.”
Three real examples
Maple Street extension
Rear extension, Denver
6 weeks
Larkspur kitchen
Renovation, Boulder
3 weeks
Cedar Ridge house
New home, Evergreen
10 weeks
What we handle for you
Drawings, structural calculations, the application and every correction. You sign the forms and we chase the rest.
How to start
Open the estimator for a range and a rough programme. The permit time is part of the written programme you get with the fixed price.